Issue - meetings

Chris

Meeting: 20/01/2010 - Strategic Planning Committee (Item 9)

9 Amesbury: Stonehenge Visitor Centre - Proposed Listed Building Consent to Move the Cross at Airman's Corner (Proposed Development S/2009/1528).

A report by the Case Officer is attached.

Supporting documents:

Minutes:

On considering a report by the Service Director, Development,

 

Resolved:     Following referral to the secretary of state and completion of a legal agreement, to grant listed building consent subject to the following conditions –

 

1)      The works for which Listed Building Consent is hereby granted shall be begun before the expiration of three years from the date of this consent.

 

REASON:  To comply with the provisions of Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990 as amended by the Planning and Compulsory Purchase Act 2004.

 

2)      No development shall commence within the area indicated outlined in red on the approved plans until:

 

a)            A written programme of archaeological investigation, which should include on-site work and off-site work such as the analysis, publishing and archiving of the results, has been submitted to and approved by the Local Planning Authority; and

 

b)            The approved programme of archaeological work has been carried out in accordance with the approved details.

 

REASON:  To enable the recording of any matters of archaeological interest.

 

3)            Prior to the commencement of this development a timetable shall be submitted and approved in writing by the local authority, setting out the timing for the removal and replacement of the airman’s cross memorial. The development shall be carried out in accordance with the agreed timetable.

 

REASON: To allow the local planning authority to ensure that the airman’s cross is not erected independently of the main visitor centre to which it will relate

 

4)      Prior to the removal of the Airmans Cross for repairs a method statement shall be submitted for the dismantling and rebuilding of the memorial along with a specification for any repairs to be carried out. This information shall be approved by the local planning authority prior to the commencement of development on the Airmans Cross.

 

REASON: To ensure that the detail of the repair and dismantling of the structure is undertaken in a manner which will not damage the listed structure.

 

INFORMATIVE

 

In relation to condition three the local planning authority will wish to see any timetable for the removal and replacement of the airman’s cross memorial to show how this memorial will be removed and replaced during the construction works for the main visitor centre.

 

 

 

 

(Duration of meeting: 3.00pm – 5.00pm)

 

The Officer who has produced these minutes is Roger Bishton, Democratic &

Members’ Services, direct line (01225) 713035 or e-mail

 roger.bishton@wiltshire.gov.uk

Press enquiries to Communications, direct line (01225) 713114/71311