8.1    S/2009/0307 - Cross Keys,Fovant Salisbury

 

Public Participation:

Mr Barrett spoke in objection to the application

Mrs P Storey (applicant) spoke in support of the application

Mr Knowles (Fovant Parish Council) spoke in objection to the application

 

  Resolved

 

  That planning permission be GRANTED for the following reasons:

 

 

The proposed development is considered to be well designed resulting in a significant visual improvement to the existing building whilst providing a community use against which no demonstrable harm is evident. The proposal is considered to be in accordance with the aims and objectives of policies G1 Sustainable development, G2 Criteria for development, D3 Extensions, CN3 Character and setting of listed buildings, CN4 Change of use of listed buildings, CN8 development in conservation areas.

 

(1) The change of use  hereby permitted and the construction of the extension hereby permitted  shall be begun before the expiration of three years from the date of this permission.

 

REASON:  To comply with the provisions of Section 91 of the Town and Country Planning Act 1990 as amended by the Planning and Compulsory Purchase Act 2004.

 

(2)  No construction of the extension hereby permitted shall commence until details and samples of the materials to be used for the external walls and roofs have been submitted to and approved in writing by the Local Planning Authority.  Development shall be carried out in accordance with the approved details.

 

REASON: In the interests of visual amenity and the character and appearance of the area.

 

POLICY- G2 General Development Control Criteia D3 Design of Extensions

 

(3) No construction of the extension shall commence  on site until a sample panel of stonework, not less than 1 metre square, has been constructed on site, inspected and approved in writing by the Local Planning Authority.  The panel shall then be left in position for comparison whilst the development is carried out. Development shall be carried out in accordance with the approved sample.

 

REASON: In the interests of visual amenity and the character and appearance of the area.

 

POLICY-G2  General Development Control Criteria D3 Design of Extensions

 

(4) No external construction works shall commence on site  until details of the design, external appearance and decorative finish of all railings, fences, gates, walls, bollards and other means of enclosure have been submitted to and approved in writing by the Local Planning Authority.  Development shall be carried out in accordance with the approved details prior to the development being brought into use

 

REASON:  In the interests of visual amenity and the character and appearance of the area.

 

POLICY-G2 General Development Control Criteria

 

(5) No  external construction works shall commence on site  until details of all new or replacement external chimneys, flues, extract ducts, vents, grilles and meter housings have been submitted to and approved in writing by the Local Planning Authority.  The works shall be carried out in accordance with the approved details.

 

REASON: In the interests of preserving the character and appearance of the listed building and its setting.

 

POLICY-CN5 Preservation of character and setting of  ...  view the full minutes text for item 8