Agenda item

15/05079/FUL - Withleigh, Melksham

Minutes:

The Senior Planning Officer outlined the report that recommended that the application be approved with conditions.

 

Brian Inns and Doug Tuckerman spoke in objection to the application; and David William spoke in support of the application.

 

Cllr Jonathon Seed spoke on behalf of the local member Cllr Jon Hubbard.

 

Issues discussed in the course of the presentation and debate included: the location of the proposed development and the size and elevation of the proposed building; the setting of the proposal and its proximity to the conservation area and other listed buildings; the impact of the proposals on the trees and landscaping on the site; the impact of the proposals on the neighbouring properties, and the distance of the proposals from neighbouring properties; the car parking spaces proposed and the views of the highway officers.

 

In questioning the Senior Planning Officer, the Committee sought clarity on the proposed allocation of funding arising from the draft s106 agreement, the impact of the cost of the new crossing on the affordable housing contribution; and the officer’s view that a condition on the permission may not be considered reasonable.

 

Having been put to the vote, the meeting;

 

Resolved that the Area Development Manager be authorised to grant planning permission, subject to the conditions set out below, on prior completion of a Section 106 legal agreement for bus stops, a pedestrian crossing and off site affordable housing contribution.

 

1

The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

 

REASON:   To comply with the provisions of Section 91 of the Town and Country Planning Act 1990 as amended by the Planning and Compulsory Purchase Act 2004.

 

 

2

No development shall commence on site until:

 

a)      A written programme of archaeological investigation, which should include on-site work and off-site work such as the analysis, publishing and archiving of the results, has been submitted to and approved by the Local Planning Authority; and

b)      The approved programme of archaeological work has been carried out in accordance with the approved details.

 

REASON: The application contained insufficient information to enable this matter to be considered prior to granting planning permission and the matter is required to be agreed with the Local Planning Authority before development commences in order that the development is undertaken in an acceptable manner, to enable the recording of any matters of archaeological interest.

 

 

3

No development shall commence on site until an investigation of the history and current condition of the site to determine the likelihood of the existence of contamination arising from previous uses has been carried out and all of the following steps have been complied with to the satisfaction of the Local Planning Authority: 

 

Step (i)            A written report has been submitted to and approved by the Local Planning Authority which shall include details of the previous uses of the site for at least the last 100 years and a description of the current condition of the site with regard to any activities that may have caused contamination.  The report shall confirm whether or not it is likely that contamination may be present on the site.

 

Step (ii)            If the above report indicates that contamination may be present on or under the site, or if evidence of contamination is found, a more detailed site investigation and risk assessment should be carried out in accordance with DEFRA and Environment Agency's "Model Procedures for the Management of Land Contamination CLR11" and other authoritative guidance and a report detailing the site investigation and risk assessment shall be submitted to and approved in writing by the Local Planning Authority.  

 

Step (iii)           If the report submitted pursuant to step (i) or (ii) indicates that remedial works are required, full details have been submitted to the Local Planning Authority and approved in writing and thereafter implemented prior to the commencement of the development or in accordance with a timetable that has been agreed in writing by the Local Planning Authority as part of the approved remediation scheme. On completion of any required remedial works the applicant shall provide written confirmation to the Local Planning Authority that the works have been completed in accordance with the agreed remediation strategy.

 

REASON:  The application contained insufficient information to enable this matter to be considered prior to granting planning permission and the matter is required to be agreed with the Local Planning Authority before development commences in order that the development is undertaken in an acceptable manner, to ensure that land contamination can be dealt with adequately prior to the use of the site hereby approved by the Local Planning Authority.

4

No development shall commence on site until a scheme for the discharge of foul water from the site has been submitted to and approved in writing by the Local Planning Authority.  The development shall not be occupied until the drainage details have been constructed in accordance with the approved details.

 

REASON: The application contained insufficient information to enable this matter to be considered prior to granting planning permission and the matter is required to be agreed with the Local Planning Authority before development commences in order that the development is undertaken in an acceptable manner.

5

No development shall commence on site until a scheme for the discharge of surface water from the site (including surface water from the access / driveway), incorporating sustainable drainage details together with permeability test results to BRE365, has been submitted to and approved in writing by the Local Planning Authority. 

 

Should the submitted storm water drainage system, include a connection to the main sewer, and thus incorporating the use of a pumped system the application will need to include details of the pumping station and storage system, details of ownership, future maintenance liability and maintenance regime and standby power arrangements

The development shall not be occupied until the surface water drainage details have been constructed in accordance with the approved details.

 

REASON: The application contained insufficient information to enable this matter to be considered prior to granting planning permission and the matter is required to be agreed with the Local Planning Authority before development commences in order that the development is undertaken in an acceptable manner.

6

No development shall commence on site until a noise and dust management  plan for both the demolition and construction phases has been submitted to and approved in writing by the Local Planning Authority. The development shall then be carried out in accordance with the approved details.

 

REASON: The application contained insufficient information to enable this matter to be considered prior to granting planning permission and the matter is required to be agreed with the Local Planning Authority before development commences in order that the development is undertaken in an acceptable manner.

7

No development shall commence on site until details of the provision of bat roosting features into the new buildings, including integral boxes/bricks/tubes and access into parts of the roof space, and bat boxes in trees, including the Ash tree in the south-eastern corner of the site, and nesting opportunities for House martin, House sparrow, Starling and Swift and a plan showing the locations and types of all bat and bird features has been submitted to and approved in writing by the local planning authority.  including a plan showing the locations and types of all bat and bird features. The approved details shall be implemented before the building hereby approved is first occupied.

 

REASON: To provide additional roosting for bats and nesting birds as a biodiversity enhancement, in accordance with paragraph 118 of the National Planning Policy Framework and Section 40 of the Natural Environment and Rural Communities Act 2006.

8

No development shall commence on site until the exact details and samples of the materials to be used for the external walls and roofs have been submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details.

 

REASON: The application contained insufficient information to enable this matter to be considered prior to granting planning permission and the matter is required to be agreed with the Local Planning Authority before development commences in order that the development is undertaken in an acceptable manner, in the interests of visual amenity and the character and appearance of the area

9

No part of the development hereby approved shall be occupied until details of the obscure glazing used in the windows shown on the approved plans has been submitted to and approved in writing by the Local Planning Authority, and; the obscure glazing has been installed in accordance with the approved details. The obscure glazing shall be maintained in accordance with the approved details in perpetuity.

 

REASON: In the interests of residential amenity and privacy.

10

Unit 2 shall not be occupied until the side windows serving the living room and bedroom 1 have been glazed with obscure glass to the level agreed in condition 9. The windows shall be maintained with obscure glazing in perpetuity.

 

REASON:  In the interests of residential amenity and privacy.

11

The windows serving the refuse room shown on drawing annotated as proposed ground floor plan shall be fixed shut and shall remain as such in perpetuity.

 

REASON: In the interest of neighbouring amenity.

12

No part of the development hereby approved shall be occupied until details of external lighting within the site have been submitted to and approved in writing by the Local Planning Authority. The development shall then be carried out in accordance with the approved details.

 

REASON: In the interest of amenity and neighbouring amenity.

13

No part of the development hereby permitted shall be occupied until the access, turning area, visibility splay and parking spaces have been completed in accordance with the details shown on the approved plans. The areas shall be maintained for those purposes at all times thereafter.

 

REASON: In the interests of highway safety.

14

No dwelling shall be occupied, until details of the privacy screen walls detailed on the approved plans and for units 14, 17, 19, 22, 24, 25 & 30 have been submitted to and approved in writing by the Local Planning Authority, and; the privacy screen walls in respect of each dwelling have been erected in accordance approved details. The approved screen walls shall be retained and maintained as such at all times thereafter.

 

REASON: To prevent overlooking & loss of privacy to neighbouring property

15

All soft landscaping comprised in the approved plans shall be carried out in the first planting and seeding season following the first occupation of the building(s) or the completion of the development whichever is the sooner;  All shrubs, trees and hedge planting shall be maintained free from weeds and shall be protected from damage by vermin and stock. Any trees or plants which, within a period of five years, die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local planning authority. 

All hard landscaping shall also be carried out in accordance with the approved details prior to the occupation of any part of the development or in accordance with a programme to be agreed in writing with the Local Planning Authority.

 

REASON: To ensure a satisfactory landscaped setting for the development and the protection of existing important landscape features.

16

Demolition or construction works shall not take place outside 08:00 hours to 18:00 hours Mondays to Fridays and 08:30 hours to 13:00 hours on Saturdays nor at any time on Sundays or Bank Holidays.

 

REASON: In the interest of neighbouring amenity

17

No burning of waste or other material shall take place on the site

 

REASON: In the interest of neighbouring amenity

18

The dwellings hereby approved shall achieve at least Level 4 of the Code for Sustainable Homes. No dwelling shall be occupied until a final Code Certificate has been issued for it certifying that Code Level 4 as a minimum has been achieved.

 

REASON: In the interest of Sustainable Construction

19

The development hereby permitted shall be carried out in accordance with the following approved plans:

Site Plan, Proposed Roof Plan, Tree Protection Plan, Landscape Strategy Plan, Planning Drainage Strategy, Proposed Elevations 2 of 2,  Proposed Ground Floor Plan, Proposed First Floor Plan, Proposed Second Floor Plan, received 26th May 2015

Proposed Elevations 1 of 2 received 26th June 2015

 

REASON: For the avoidance of doubt and in the interests of proper planning.

1

INFORMATIVE TO APPLICANT:

This permission shall be read in conjunction with an Agreement made under Section 106 of the Town and Country Planning Act, 1990 (dated TBC).

2

The applicant is advised that the development hereby approved represents chargeable development under the Community Infrastructure Levy Regulations 2010 (as amended) and Wiltshire Council's CIL Charging Schedule. A separate Community Infrastructure Levy Liability Notice will be issued by the Local Planning Authority. Should you require further information with regards to CIL please refer to the Council's Website

www.wiltshire.gov.uk/planninganddevelopment/planningpolicy/communityinfrastructurelevy

3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

INFORMATIVE TO APPLICANT:

Please note that this consent does not override the statutory protection afforded to any protected species. All British bat species are protected under The Conservation of Habitats and Species Regulations 2010 (as amended), which implements the EC Directive 92/43/EEC in the United Kingdom, and the Wildlife and Countryside Act 1981 (as amended). This protection extends to individuals of the species and their roost features, whether occupied or not. If bats are discovered, all works should stop immediately and a licensed bat worker should be contacted for advice on any special precautions before continuing (including the need for a derogation licence from Natural England).

 

 

The applicant is also advised works should not take place that will harm nesting birds from March to August inclusive. All British birds (while nesting, building nests and sitting on eggs), their nests and eggs (with certain limited exceptions) are protected by law under Section 1 of the Wildlife and Countryside Act 1981 (as amended) and the Countryside and Rights of Way Act 2000. If birds are nesting on/in or within the vicinity of the proposed development, work should be undertaken outside the breeding season for birds to ensure their protection, i.e. works should only be undertaken between August and February. Further advice on the above can be sought from the Council Ecologists.

Please note that Council offices do not have the facility to receive material samples. Please deliver material samples to site and inform the Planning Officer where they are to be found.

Admin Note: Councillor Ernie Clark voted against the proposals.

 