The Chairman invited Steve Wilson (Wiltshire
Council - Local Roads Manager – Southern Division) to give an
update on forthcoming works planned by the Highways Agency to the
Countess Roundabout (A303 / A345 junction).
Steve reported that the works had been
proposed by the Highways Agency to improve the safety and capacity
of the junction. However, Wiltshire
Council highways officers and the Police had been involved in the
early planning stages, in particular regarding the need to minimise
disruption to the local community and local road network.
The original plan had been for a 21-week
programme of works, with strategic, long distance traffic being
diverted from the A303 onto the local road network. However, following discussion this had been
revised to use a contraflow
arrangement, to keep the A303 traffic off the local
roads. This would also result in a
shorter period of works, with around 12 weeks estimated on the
outline timescale on page 44 of the agenda. Advance signage would also be used at either end
of the A303 to divert strategic traffic onto alternative routes
such as the M4/M5 corridor, and to the north and south of Amesbury
to encourage A345 traffic to seek other routes such as the
A338/A360.
The Chairman thanked Steve for the
presentation and invited questions and comments from the floor:
- In general, it was considered that
the works would enhance both the strategic and the local road
network.
- It was confirmed that Wiltshire
Council were seeking to co-ordinate highways works in the area to
avoid other roadworks continuing in the
area at the same time as these works.
It was noted that the roadworks in
Amesbury Town Centre were due to be completed by the end of the
following week.
- Members emphasised the need for the
Highways Agency to undertake a clear and comprehensive
communications plan, with local people being made aware of the
diversion routes, and plenty of advance signage to minimise impact
on local roads.
- In response to questions regarding
the penalty for overrunning the agreed timescale, Steve referred to
the representative of Balfour Beatty Mott Macdonald (BBMM), the
Highways Agency’s contractors for the scheme. It was noted that any overrun in terms of time or
budget would result in a reduction in the profits of the company
from that project.
- In relation to street lighting, it
was reported that this would be upgraded to comply with
guidelines.
- In response to a question regarding
temporary weight restrictions on the diversion routes to reduce the
impact of large lorries using the local
road network, Steve undertook to clarify whether this had been
included in the Traffic Regulation Order.
- A local resident who lived adjacent
to the roundabout expressed concern regarding the proposed lane
widening. He sought clarification that
the additional lane width would be taken from the central
reservation. The representatives of
BBMM undertook to speak to the resident outside of the meeting, and
to explain the detail of this element of the works.
- There was discussion regarding the
proposed installation of traffic lights, with some people
suggesting that this should only operate during peak times, to
allow local traffic to cross freely at other times. It was also suggested that traffic would often
back up from King Barrow ridge, and so traffic lights would be
ineffectual if traffic was stationary on the
roundabout. Further to a suggestion of
box junctions, Inspector Martyn Sweett commented that enforcement
of these would be restricted by available resources.
- In relation to the operation of the
traffic signals, a representative of BBMM explained that this would
be controlled by the traffic on approach to the junction, measured
by loops placed on the approach roads.
It was agreed that the Area Board should
received regular progress updates on this project, and that a
representative of the Highways Agency or BBMM should be invited to
attend the next meeting of the Area Board to present the plans in
more detail. In addition, further
information was required on the following specific points.
- Confirmation of whether the
temporary Traffic Regulation Order (TRO) for the diversion routes
includes any temporary weight restriction. (Following the meeting it was confirmed that temporary weight
restrictions were not considered viable and/or suitable and had not
been included in the TRO).
- Clarification on how the traffic
lights/box junctions would prevent traffic from backing up and
blocking the roundabout. (Following the meeting BBMM confirmed that the
scheme included queue detection equipment on the A303 westbound
carriageway, approximately 300m west of Countess
Roundabout. This was designed to detect
when queues reached this point from the “dual carriageway
merge to one lane”, and adjust the signals operations
accordingly to mitigate the risk of A303 traffic blocking the
roundabout).
- The final timescale, including the
estimated minimum/maximise duration of the works. (Following the
meeting, BBMM confirmed in a letter to stakeholders, that work
was due to start on Monday 17 January, and would take place seven
days per week during daylight hours, with 24-hour working wherever
practical. The scheme was expected to
continue for approximately 17 weeks.
The 17-week period included site establishment, the main body of
works over a 12-week period, an allowance for the Easter holiday
traffic management embargo, and commissioning of the traffic
signals).