Update on The Vale HWBC (Cllr Paul Oatway)

Meeting: 11/09/2017 - Pewsey Area Board (Item 46)

Update on The Vale HWBC (Cllr Paul Oatway)

Minutes:

Cllr Paul Oatway gave an update on the facility, stating that it was a demolition site, but that building works were underway. He explained that there had been an issue with the amount of asbestos found on the site. The Board were advised that there had been a complaint raised, surrounding the diversion of a footpath, which is currently used by a small number of residents to access the school. The cost of providing this footpath was estimated to cost £5000 and Cllr Oatway stated that he did not see this as value for money, as the money could be spent for the benefit of the wider community.