Michael
Sammes, Vanessa Robshaw and Michael Gibbons spoke against the
application. John Bostock spoke in
favour of the application.
The Planning
Officer introduced the report which was an application for the
erection of 6 dwellings, which had been reported to Committee on 26
October 2016 and deferred for further consideration of three
issues: the possibility for an
environmental corridor, an assessment of the Japanese Knotweed
issues on the site, and vicinity, and the possibility of traffic
calming measures sympathetic to the character of the conservation
area. Officers explained that all issues had been considered and
addressed by the proposed conditions in the report.
The officer
showed pictures and diagrams which identified proposed location and
specifications of the build, it was highlighted that slight
alterations had been made to the layout, moving the proposed houses
further into the site and therefore further away from neighbours,
alterations had also been made to avoid the root zone of a beech
tree on the site. The environmental corridor was now included in
the plans with minor alterations and with minimal impact. The
Knotweed issue had been addressed by a condition to ensure the
removal of the species prior to commencing the building works. The
traffic calming measures were to be dealt with by a revised road
layout and protection zones, alternative materials appropriate to
the conservation area status of the site had been proposed by the
applicant and agreed by officers.
The Chairman
invited members to ask technical questions and there were
none.
The Chairman
invited members of the public to make representations, as detailed
above.
In response
to statements from the public, the Planning Officer explained that
the Committee was already familiar with the application; members
were considering the three issues deferred from a previous
Committee meeting, and key changes to the proposed consent were in
response to the matters Committee had sought further clarity on
when it was last debated. It was explained that public consultation
on the revised plans had not been undertaken since the overall
impact of the proposed development on neighbours had been lessened
in comparison to the previous proposals. The proposed condition on
Knotweed had been considered appropriate by the Council’s
Ecologist.
Cllr Peter
Hutton moved the officer’s recommendation, subject to the
conditions in the report and a requirement that a completion survey
be carried out post eradication of the Knotweed, and an informative
referring the applicant to the maximum fine for allowing Knotweed
to spread, the wording of which to be determined by officers. This
was seconded by Cllr Howard Greenman.
In the
debate that followed members considered the impact of the Japanese
Knotweed and agreed the development to be acceptable and an
improvement to the previous proposal.
RESOLVED:
That authority is DELEGATED to the Head of
Development Management to
GRANT planning permission, subject to conditions
listed below and completion of a S106 legal agreement within six
months of the date of the resolution of this Committee, and subject
to an amendment to the proposed condition in respect of Knotweed in
order to secure a completion survey of the land in question post
eradication and removal works to confirm removal and also an
Informative to be added referring the applicant to the maximum fine
permissible if Knotweed is allowed to spread. Authority is
delegated to the Head of Service to prepare appropriate wording in
this regard.
In the event of failure to complete, sign and seal
the required section 106 agreement within the defined timeframe to
then delegate authority to the Head of Development Management to
REFUSE planning permission for the following reason:-
The application proposal fails to provide the
necessary mitigation in line with Policies CP50, CP51 and CP58 of
the Wiltshire Core Strategy (Adopted January 2015) and Paras 7, 14 & 17 of the National Planning
Policy Framework March 2012.
- The development hereby permitted shall be begun before the
expiration of three years from the date of this
permission.
REASON: To comply with the provisions of Section 91
of the Town and Country Planning Act 1990 as amended by the
Planning and Compulsory Purchase Act 2004.
- The development hereby permitted shall be carried out in
accordance with the following approved plans:
- Drawing No: 1631 - 01 (as submitted 20/09/2016) - Site
Plan
- Drawing No: 1631 - 02 REV H (as submitted 13/12/2016) - Site
Layout
- Drawing No: 1631 - 03 REV F (as submitted 13/12/2016) –
Street Elevations & Sections
- Drawing No: 1631 - 04 REV D (as submitted 13/12/2016) –
Rear elevations & Sections
- Drawing No: 1631 - 05 REV G (as submitted 13/12/2016) - Parking
Provision
- Drawing No: 1631 - 06 REV K (as submitted 16/12/2016) - Drainage
Strategy
- Drawing No: 1631 - 07 REV H (as submitted 13/12/2016) –
Landscaping Layout
- Drawing No: 1631 - Plot1fp (as submitted 13/12/2016) - Plot 1
Floor Plan and Elevations
- Drawing No: 1631 - Plot2el (as submitted 13/12/2016) - Plot 2
Floor Plan and Elevations
- Drawing No: 1631 REV A - Plot3fp (as submitted 13/12/2016) -
Plot 3 Floor Plans
- Drawing No: 1631 REV A - Plot3el (as submitted 13/12/2016) -
Plot 3 Elevations
- Drawing No: 1631 REV A - Plot4el (as submitted 13/12/2016) -
Plot 4 Elevations
- Drawing No: 1631 REV A - Plot4fp (as submitted 13/12/2016) -
Plot 4 Floor Plan
- Drawing No: 1631 REV B - Plot5/6fp (as submitted 13/12/2016) -
Plot 5 & 6 Floor Plan
- Drawing No: 1631 REV B- Plot5/6el (as submitted 13/12/2016) -
Plot 5 & 6 Elevations
- Drawing No: 1631 REV B - gar/encl (as submitted 13/12/2016) -
Garages and Enclosure plans.
- Drawing No: 1631 0700 Rev P5 (13/12/2016) Engineering Layout and
Details
- D37 36 P2 Rev A (13/12/2016)
- D37 36 P1 (13/12/2016)
- D37 36 P3 (13/12/2016)
- Extended Phase 1 Habitat Survey and Assessment by Alder Ecology
(May 2013)
- Ecological Assessment by Tyler Grange (June
2016)
- FRA Addendum Report by Craddys (June
2016)
REASON: For the avoidance of doubt and in the
interests of proper planning.
- No development shall commence on site until the exact details
and samples of the materials to be used for the external walls and
roofs have been submitted to and approved in writing by the Local
Planning Authority. Development shall be carried out in accordance
with the approved details.
REASON: The matter is required to be agreed with the
Local Planning Authority before development commences in order that
the development is undertaken in an acceptable manner, in the
interests of visual amenity and the character and appearance of the
area
4.
No development shall commence on site
(including any works of demolition), until a Construction Method
Statement, which shall include the following:
- the parking of vehicles of site operatives and
visitors;
- loading and unloading of plant and materials;
- storage of plant and materials used in constructing the
development;
- the erection and maintenance of security hoarding including
decorative displays and facilities for public viewing, where
appropriate;
- measures to control the emission of dust and dirt during
construction;
- a scheme for recycling/disposing of waste resulting from
demolition and construction works; and
- hours of construction, including deliveries;
Has been submitted to, and approved in writing by,
the Local Planning Authority. The approved Statement shall be
complied with in full throughout the construction period. The
development shall not be carried out otherwise than in accordance
with the approved construction method statement.
REASON: The matter is required to be agreed with the
Local Planning Authority before development commences in order that
the development is undertaken in an acceptable manner, to minimise
detrimental effects to the neighbouring amenities, the amenities of
the area in general, detriment to the natural environment through
the risks of pollution and dangers to highway safety, during the
construction phase.
- A Landscape and Ecological Management Plan (LEMP) shall be
submitted to, and approved in writing by, the Local Planning
Authority before commencement of the development. The content of
the LEMP shall include, but not necessarily be limited to, the
following information:
- Description and evaluation of features to be
managed;
- Landscape and ecological trends and constraints on site that
might influence management;
- Aims and objectives of management;
- Appropriate management options for achieving aims and
objectives;
- Prescriptions for management actions;
- Preparation of a work schedule (including an annual
work);
- Details of the body or organisation responsible for
implementation of the plan;
- Ongoing monitoring and remedial measures;
- Details of how the aims and objectives of the LEMP will be
communicated to future occupiers of the
development.
The LEMP shall also include details of the legal and
funding mechanism(s) by which the long-term implementation of the
plan will be secured by the developer with the management
body/ies responsible for its delivery.
The plan shall also set out (where the results from monitoring show
that the conservation aims and objectives of the LEMP are not being
met) how contingencies and/or remedial action will be identified,
agreed and implemented. The LEMP shall be implemented in full in
accordance with the approved details.
REASON: The matter is required to be agreed with the
Local Planning Authority before development commences in order that
the development is undertaken in an acceptable manner, to ensure
adequate protection, mitigation and compensation for protected
species, priority
- No development shall commence on site (including demolition,
ground works, vegetation clearance) until a Construction
Environmental Management Plan (CEMP) has been submitted to and
approved in writing by the local planning authority. The CEMP shall
include, but not necessarily be limited to, the
following:
- Protection of trees including details of root protection areas
and fencing;
- Mitigation for any potential tree bat roosts to be
removed;
- An updated badger survey and mitigation
strategy;
- A reptile mitigation strategy including methods to be applied
during the construction phase and details of the proposed receptor
site including long-term maintenance.
- Protection of breeding birds.
- Ongoing monitoring, including compliance checks by a competent
person(s) during construction and immediately post-completion of
construction works.
The approved CEMP shall be adhered to and
implemented throughout the construction period strictly in
accordance with the approved details.
A report prepared by a competent person(s),
certifying that the required mitigation and/ or compensation
measures identified in the CEMP have been completed to their
satisfaction, shall be submitted to the Local Planning Authority
within 3 months of the date of
substantial completion of the development or at the end of the next
available planting season, whichever is
the sooner.
REASON: To ensure adequate protection, mitigation
and compensation for protected species, priority species and
priority habitats.
- No demolition, site clearance or development shall commence on
site until an Arboricultural Method
Statement (AMS) prepared by an arboricultural consultant providing comprehensive
details of construction works in relation to trees has been
submitted to, and approved in writing by, the Local Planning
Authority. All works shall subsequently be carried out in strict
accordance with the approved details. In particular, the method
statement must provide the following:-
- A specification for protective fencing to trees during both
demolition and construction phases which complies with BS5837:2012
and a plan indicating the alignment of the protective
fencing;
- A specification for scaffolding and ground protection within
tree protection zones in accordance with British Standard 5837:
2012;
- A schedule of tree works conforming to British Standard 3998:
2010;
- Details of general arboricultural
matters such as the area for storage of
materials, concrete mixing and use of fires;
- Plans and particulars showing the siting of the service and piping infrastructure.
The detailed landscaped plan should be not less than 1:200 scale,
showing the position of any trees proposed to be retained and the
positions and routes of all proposed and existing pipes, drains,
sewers, and public services, including gas, electricity, telephone
and water.
- A full specification for the construction of any arboriculturally sensitive structures and sections
through them, including the installation of boundary treatment
works, the method of construction of the access driveway including
details of the no-dig specification and extent of the areas of the
driveway to be constructed using a no-dig
specification;
- Details of the works requiring arboricultural supervision to be carried out by the
developer’s arboricultural
consultant, including details of the frequency of supervisory
visits and procedure for notifying the Local Planning Authority of
the findings of the supervisory visits; and
- Details of all other activities, which have implications for
trees on or adjacent to the site.
- Day and sunlight calculations must be submitted in accordance
with Building
- Research Establishment guidance and British Standards 8206 Part
2: 2008 Light for Buildings Part 2 - Code of practice for
daylighting.
- In order that trees to be retained on-site are not damaged
during the construction works and to ensure that as far as possible
the work is carried no demolition, site clearance or development
should commence on site until a precommencement site meeting has been held,
attended by the developer’s arboricultural consultant, the designated site
foreman and a representative from the Local Planning Authority, to
discuss details of the proposed work and working
procedures.
- Subsequently and until the completion of all site works, site
visits should be carried out on a weekly basis by the
developer’s arboricultural
consultant. A report detailing the results of site supervision and
any necessary remedial works undertaken or required should then be
submitted to the Local Planning Authority.
- Any approved remedial works shall subsequently be carried out
under strict supervision by the arboricultural consultant following that
approval.
REASON: The matter is required to be agreed with the
Local Planning Authority before development commences in order that
the development is undertaken in an acceptable manner, in order
that the Local Planning Authority may be satisfied that the trees
to be retained on and adjacent to the site will not be damaged
during the construction works and to ensure that as far as possible
the work is carried out in accordance with current best practice
and section 197 of the Town & Country Planning Act
1990.
- No demolition, site clearance or development shall commence on
site, and; no equipment, machinery or materials shall be brought on
to site for the purpose of development, until a Tree Protection
Plan showing the exact position of each tree/s and their protective
fencing in accordance with British Standard 5837: 2012:
“Trees in Relation to Design, Demolition and Construction
-Recommendations”; has been submitted to and approved in
writing by the Local Planning Authority, and;
The protective fencing shall be erected in
accordance with the approved details. The protective fencing shall
remain in place for the entire development phase and until all
equipment, machinery and surplus materials have been removed from
the site. Such fencing shall not be removed or breached during
construction operations.
No retained tree/s shall be cut down, uprooted or
destroyed, nor shall any retained tree/s be topped or lopped other
than in accordance with the approved plans and particulars. Any
topping or lopping approval shall be carried out in accordance
British Standard 3998: 2010 “Tree Work –
Recommendations” or arboricultural techniques where it can be
demonstrated to be in the interest of good arboricultural practise.
If any retained tree is removed, uprooted, destroyed
or dies, another tree shall be planted at the same place, at a size
and species and planted at such time, that must be agreed in
writing with the Local Planning Authority.
No fires shall be lit within 15 metres of the
furthest extent of the canopy of any retained trees or hedgerows or
adjoining land and no concrete, oil, cement, bitumen or other
chemicals shall be mixed or stored within 10 metres of the trunk of
any tree or group of trees to be retained on the site or adjoining
land.
[In this condition “retained tree” means
an existing tree which is to be retained in accordance with the
approved plans and particulars; and paragraphs above shall have
effect until the expiration of five years from the first occupation
or the completion of the development, whichever is the
later].
REASON: The matter is required to be agreed with the
Local Planning Authority before development commences in order that
the development is undertaken in an acceptable manner, to enable
the Local Planning Authority to ensure the retention of trees on
the site in the interests of visual amenity.
- No development shall commence on site until a scheme for the
discharge of surface water from the site (including surface water
from the access / driveway), incorporating sustainable urban
drainage details has been submitted to and approved in writing by
the Local Planning Authority. The development shall not be first
occupied until surface water drainage has been constructed in
accordance with the approved scheme.
REASON: To ensure that the development can be
adequately drained.
- No development shall commence on site until a scheme for the
discharge of surface water from the highway fronting the site has
been submitted to and approved in writing by the Local Planning
Authority. The development shall not be first occupied until the
highway drainage scheme has been constructed in accordance with the
approved scheme.
REASON: To ensure that the development can be
adequately drained
- No development shall commence on site until details of the works
for the disposal of sewerage including the point of connection to
the existing public sewer have been submitted to and approved in
writing by the Local Planning Authority. No dwelling shall be first
occupied until the approved sewerage details have been fully
implemented in accordance with the approved plans.
REASON: The matter is required to be agreed with the
Local Planning Authority before development commences in order that
the development is undertaken in an acceptable manner, to ensure
that the proposal is provided with a satisfactory means of drainage
and does not increase the risk of flooding or pose a risk to public
health or the environment.
- Notwithstanding the provisions of the Town and Country Planning
(General Permitted Development) (England) Order 2015 (or any Order
revoking or re-enacting or amending that Order with or without
modification), there shall be no additions to, or extensions or
enlargements of any building forming part of the development hereby
permitted.
REASON: In the interests of the amenity of the area
and to enable the Local Planning Authority to consider individually
whether planning permission should be granted for additions,
extensions or enlargements.
- Notwithstanding the provisions of the Town and Country Planning
(General Permitted Development) (England) Order 2015 (or any Order
revoking or re-enacting or amending that Order with or without
modification), no gates, fences, walls or other means of enclosure,
other than those shown on the approved plans, shall be erected or
placed anywhere on the site.
REASON: In the interests of visual
amenity.
- Notwithstanding the provisions of the Town and Country Planning
(General Permitted Development) (England) Order 2015 (or any Order
revoking or re-enacting or amending that Order with or without
modification), the garage(s) hereby permitted shall not be
converted to habitable accommodation.
REASON: To secure the retention of adequate parking
provision, in the interests of highway safety.
- There must be no ground raising or obstruction to flow on
existing land at or below the 1 in 100 year flood level
(45.57mAOD).
REASON: In the interests of flood
prevention
- The dwellings hereby approved shall achieve a level of energy
performance at or equivalent to Level 4 of the Code for Sustainable
Homes. No dwelling shall be occupied until evidence has been issued
and submitted to, and approved in writing by, the local planning
authority certifying that this level or equivalent has been
achieved.
REASON: To ensure that the objectives of sustainable
development equal or equivalent to those set out in Policy CP41 of
the Wiltshire Core Strategy are achieved.
- No development including vegetation removal / management, site
clearance, ground works or intrusive site investigations, shall
commence until a detailed method statement for the
removal/eradication of Japanese knotweed on the site has been
submitted to and approved in writing by the Local Planning
Authority. The method statement shall include proposed measures to
prevent the spread of Japanese Knotweed during any operations in
accordance with best practice, and ensure the safe disposal of
invasive plant material as required. It shall also contain measures
to ensure that any soils brought to the site are free of the seeds
/ root / stem of any invasive plant covered under the Wildlife and
Countryside Act 1981. Development shall be carried out in strict
accordance with the approved method statement.
- No part of the development hereby permitted shall be first
occupied until the access, turning area and parking spaces have
been completed in accordance with the details shown on the approved
plans. The areas shall be maintained for those purposes at all
times thereafter.
REASON: In the interests of highway
safety.
- No development shall commence on site until details of the
‘highway works’ consisting of carriageway widening /
traffic calming / lowered kerb to be formed at Baydon Lane have been submitted to, and approved in
writing by, the Local Planning Authority. The highway works shall
include the re-surfacing of the wearing course of the whole
carriageway (ie after the widening). No
part of the development shall be occupied until the ‘highway
works’ have been provided in accordance with the approved
details (numbered 1084_0700 P5 and titled ‘Engineering Layout
and Details’).
REASON: In the interests of highway
safety.
- No development shall commence on site until visibility splays at
both access points have been provided between the edge of the
carriageway and a line extending from a point 2m metres back from
the edge of the carriageway, measured along the centre line of the
access, to the points on the edge of the carriageway 25 metres from
the centre of the access in accordance with the approved plans
(numbered 1084_0700 P5 and titled ‘Engineering Layout and
Details’). Such splays shall thereafter be permanently
maintained free from obstruction to vision above a height of 0.6m
above the level of the adjacent carriageway.
REASON: In the interests of highway
safety.
- Notwithstanding the provisions of the Town and Country Planning
(General Permitted Development) Order 1995 (as amended by the Town
and Country Planning (General Permitted Development) (Amendment)
(No.2) (England) Order 2008 (or any Order revoking or re-enacting
or amending that Order with or without modification), the garage(s)
hereby permitted shall not be converted to habitable
accommodation.
REASON: To safeguard the amenities and character of
the area and in the interest of highway safety.
- INFORMATIVE TO APPLICANT: The consent hereby granted shall not
be construed as authority to carry out works on the highway. The
applicant is advised that a license may be required from
Wiltshire’s Highway Authority before any works are carried
out on any footway, footpath, carriageway, verge or other land
forming part of the highway.
- INFORMATIVE TO APPLICANT: Please note that Japanese Knotweed
waste (the plant itself or material containing its rhizomes) is
classed as a controlled/special waste and therefore needs to be
disposed of in accordance with the Environmental Protection Act
1990 and the Environmental Protection Act Duty of Care Regulations
1991. It may be necessary to inform the Environment Agency of the
intention to bury or burning Japanese Knotweed onsite. Any soils or
material contaminated with Japanese Knotweed should be disposed of
at an authorised landfill site or suitable disposal site. Please
see government guidance for further details.
https://www.gov.uk/guidance/prevent-japanese-knotweed-fromspreading
- INFORMATIVE TO APPLICANT: Any alterations to the approved plans,
brought about by compliance with Building Regulations or any other
reason must first be agreed in writing with the Local Planning
Authority before commencement of work.
- INFORMATIVE TO APPLICANT: This permission shall be read in
conjunction with an Agreement made under Section 106 of the Town
and Country Planning Act, 1990 and dated the
[INSERT].
- INFORMATIVE TO APPLICANT: The applicant should note that the
grant of planning permission does not include any separate
permission which may be needed to erect a structure in the vicinity
of a public sewer. Such permission should be sought direct from
Thames Water Utilities Ltd / Wessex Water Services Ltd. Buildings
are not normally allowed within 3.0 metres of a Public Sewer
although this may vary depending on the size, depth, strategic
importance, available access and the ground conditions appertaining
to the sewer in question.
- INFORMATIVE TO APPLICANT: The applicant should note that under
the terms of the Wildlife and Countryside Act (1981) and the
Habitats Regulations (2010) it is an offence to disturb or harm any
protected species, or to damage or disturb their habitat or resting
lace. Please note that this consent does not override the statutory
protection afforded to any such species. In the event that your
proposals could potentially affect a protected species you should
seek the advice of a suitably qualified and experienced ecologist
and consider the need for a licence from Natural England prior to
commencing works. Please see Natural England's website for further
information on protected species.
- INFORMATIVE TO APPLICANT: Please note that Council offices do
not have the facility to receive material samples. Please deliver
material samples to site and inform the Planning Officer where they
are to be found.
- INFORMATIVE TO APPLICANT: The applicant is advised that the
development hereby approved may represent chargeable development
under the Community Infrastructure Levy Regulations 2010 (as
amended) and Wiltshire Council's CIL Charging Schedule. If the
development is determined to be liable for CIL, a Liability Notice
will be issued notifying you of the amount of CIL payment due. If
an Additional Information Form has not already been submitted,
please submit it now so that we can determine the CIL liability. In
addition, you may be able to claim exemption or relief, in which
case, please submit the relevant form so that we can determine your
eligibility. The CIL Commencement Notice and Assumption of
Liability must be submitted to Wiltshire Council prior to
commencement of development. Should development commence prior to
the CIL Liability Notice being issued by the local planning
authority, any CIL exemption or relief will not apply and full
payment will be required in full and with immediate effect. Should
you require further information or to download the CIL forms please
refer to the Council's Website-
www.wiltshire.gov.uk/planninganddevelopment/planningpolicy/communityinfrastructurelevy.