Agenda item

17/05460/FUL - Land at Cedar Lodge, 3 Cove House Gardens, Ashton Keynes, Wiltshire, SN6 6NS

Minutes:

Member of the public Steve Shaw spoke against the application. Nicolas Hurst Spoke in favour of the application.

 

The Team Leader introduced the application, which was for a proposed single storey dwelling. A presentation was delivered, which displayed a site location plan, photographs of the existing site and proposed plans. It was explained that the proposed build was a modern design but would be screened by significant boundary treatments and tree planting and therefore not visually prominent in the locality, or harmful to the character and appearance of the conservation area. Officers referred to the site history and how the revised proposals sought to address previous concerns with a modern design. Officers referred to an additional condition in the Late Observations.

 

There were no technical questions.

 

Cllr Chuck Berry spoke as Local Member. He confirmed that previous concerns raised by the parish council had been addressed and their objections were removed. He sought clarity that all trees would be protected, to ensure the screening and it was confirmed that they would be protected.

 

In the debate that followed, Cllr Chuck Berry proposed the Officer’s recommendation for approval. This was seconded by Cllr Gavin Grant and approved unanimously.

 

Resolved:

 

To GRANT subject to the following conditions:

 

1 The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

 

REASON: To comply with the provisions of Section 91 of the Town and Country Planning Act 1990 as amended by the Planning and Compulsory Purchase Act 2004.

 

2 The development hereby permitted shall be carried out in accordance with the following approved plans: Proposed Elevations, Site and Block Plans (Drawing No 1652_0411b) and Proposed Ground Floor Plan (Drawing No 1652_0421b) received by the LPA 06/06/2017.

 

REASON: For the avoidance of doubt and in the interests of proper planning.

 

3 No development shall commence on site until the exact details and samples of the materials to be used for the external walls and roofs have been submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details.

 

REASON: The matter is required to be agreed with the Local Planning Authority before development commences in order that the development is undertaken in an acceptable manner, in the interests of visual amenity and the character and appearance of the area

 

4 The development shall be carried out as specified in the approved Arboricultural Report prepared by Certhia Consulting Limited dated August 2017 and shall be supervised by an Arboricultural Consultant.

 

Reason: To prevent trees on site from being damaged during construction works

 

5 No part of the development hereby approved shall be occupied until the parking area shown on the approved plans has been consolidated, surfaced and laid out in accordance with the approved details. This area shall be maintained and remain available for this use at all times thereafter.

 

REASON: To ensure that adequate provision is made for parking within the site in the interests of highway safety

 

6 No development shall commence on site (including any works of demolition), until a Construction Method Statement, which shall include the following:

a) the parking of vehicles of site operatives and visitors;

b) loading and unloading of plant and materials;

c) storage of plant and materials used in constructing the development;

d) wheel washing facilities;

e) measures to control the emission of dust and dirt during construction;

f) a scheme for recycling/disposing of waste resulting from demolition and

construction works; and

g) measures for the protection of the natural environment.

h) hours of construction, including deliveries;

Has been submitted to, and approved in writing by, the Local Planning Authority. The approved Statement shall be complied with in full throughout the construction period. The development shall not be carried out otherwise than in accordance with the approved construction method statement.

 

REASON: The matter is required to be agreed with the Local Planning Authority before development commences in order that the development is undertaken in an acceptable manner, to minimise detrimental effects to the neighbouring amenities, the amenities of the area in general, detriment to the natural environment through the risks of pollution and dangers to highway safety, during the construction phase.

 

7 Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England)Order 2015 (or any Order revoking or re-enacting or amending those Orders with or without modification), no development within Part 1, Classes A, B and E shall take place on the dwellinghouse hereby permitted or within its curtilage.

 

REASON: In the interests of the amenity of the area and to enable the Local Planning Authority to consider individually whether planning permission should be granted for additions, extensions or enlargements.

 

8 Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any Order revoking or re-enacting or amending that Order with or without modification), no buildings or structures, or gate, wall, fence or other means of enclosure, other than those shown on the approved plans, shall be erected or placed anywhere on the site on the approved plans.

 

REASON: To safeguard the character and appearance of the area.

 

9 The dwellings hereby approved shall achieve Level 4 of the Code for Sustainable Homes. No dwelling shall be occupied until a final Code Certificate for it has been issued and submitted to, and approved in writing by, the local planning authority certifying that Code Level 4 has been achieved.

 

REASON: To ensure that the objectives of sustainable development set out Policy CP41 of the Wiltshire Core Strategy are achieved.

 

10 Prior to the first occupation of the buildings a plan showing details of the green roof including species, planting density, substrate and a section at scale of 1:20 showing that adequate depth is available in terms of the construction and long term viability of the green roof, and a programme for a scheme of maintenance shall be submitted to and approved in writing by the local planning authority. The green roof shall be fully provided in accordance with the approved details prior to first occupation and thereafter retained and maintained in accordance with the approved scheme of maintenance.

 

Reason: To ensure that the green roof is suitably designed and maintained.

 

11 The drainage details shall be carried out in accordance with design and details outlined in the Supplementary Drainage System and Drawing No 1652_0421c (Proposed Ground Floor Plan) received by the LPA 21/08/2017.

 

REASON: To ensure that the development is adequately drained

 

12 INFORMATIVE TO APPLICANT:

The applicant is requested to note that this permission does not affect any private property rights and therefore does not authorise the carrying out of any work on land outside their control. If such works are required it will be necessary for the applicant to obtain the landowners consent before such works commence. If you intend carrying out works in the vicinity of the site boundary, you are also advised that it may be expedient to seek your own advice with regard to the requirements of the Party Wall Act 1996.

 

13 INFORMATIVE TO APPLICANT:

Please note that Council offices do not have the facility to receive material samples. Please deliver material samples to site and inform the Planning Officer where they are to be found.

 

14 INFORMATIVE TO APPLICANT:

Any alterations to the approved plans, brought about by compliance with Building Regulations or any other reason must first be agreed in writing with the Local Planning Authority before commencement of work.

 

15 INFORMATIVE TO APPLICANT:

The applicant should note that the grant of planning permission does not include any separate permission which may be needed to erect a structure in the vicinity of a public sewer. Such permission should be sought direct from Thames Water Utilities Ltd / Wessex Water Services Ltd. Buildings are not normally allowed within 3.0 metres of a Public Sewer although this may vary depending on the size, depth, strategic importance, available access and the ground conditions appertaining to the sewer in question.

 

16 INFORMATIVE TO APPLICANT:

The applicant is advised that the development hereby approved may represent chargeable development under the Community Infrastructure Levy Regulations 2010 (as amended) and Wiltshire Council's CIL Charging Schedule. If the development is determined to be liable for CIL, a Liability Notice will be issued notifying you of the amount of CIL payment due. If an Additional Information Form has not already been submitted, please submit it now so that we can determine the CIL liability. In addition, you may be able to claim exemption or relief, in which case, please submit the relevant form so that we can determine your eligibility. The CIL Commencement Notice and Assumption of Liability must be submitted to Wiltshire Council prior to commencement of development. Should development commence prior to the CIL Liability Notice being issued by the local planning authority, any CIL exemption or relief will not apply and full payment will be required in full and with immediate effect. Should you require further information or to download the CIL forms please refer to the Council's Website

www.wiltshire.gov.uk/planninganddevelopment/planningpolicy/communityinfrastructuelevy