Chippenham Housing Infrastructure Fund Bid

Wiltshire Council was awarded the HIF grant in November 2019. The programme now needs funding to continue its work during 2020-21 to give as much certainty as possible to meeting the HIF spending deadline of 31st March 2024. The work will include, but may not be limited to...
- contract negotiations with Homes England
- design of the proposed HIF funded distributor road
- masterplan preparation for the whole scheme area
- broad consultation on road route options and wider stakeholder management activity
- early contractor involvement in procurement
- preparation for an appropriate planning application...
...all given the highly compressed timescales.
The Programme now needs a properly constituted team to drive forward all work in parallel together with appropriate delegated authority to make the progress required

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: For Determination

Notice of proposed decision first published: 24/02/2020

Decision due: 24 Mar 2020 by Cabinet

Lead member: Cllr Bridget Wayman, Cabinet Member for Highways, Transport and Waste bridget.wayman@wiltshire.gov.uk

Lead director: Alan Richell (Programme Director, Growth and Investment)

Department: Highways and Waste

Contact: Christine Lamb Email: christine.lamb@wiltshire.gov.uk.

Consultation process

Consultation with various cabinet members and officers is appropriate at this stage

Agenda items

Documents

  • Chippenham Housing Infrastructure Fund Bid  

 